Control Schedule

A continuous activity that tracks project progress, updates the schedule to reflect actual performance, and governs approved changes to the schedule baseline.

Key Points

  • Compares actual progress against the schedule baseline to identify variances.
  • Updates the schedule model and forecasts completion dates using current performance data (e.g., SV, SPI).
  • Submits and manages change requests to the schedule baseline through integrated change control.
  • May apply techniques such as critical path analysis, what-if analysis, and schedule compression (crashing/fast tracking).

Example

Midway through a software project, several critical-path tasks slip. The project manager records actual start/finish dates, recalculates the critical path, forecasts a two-week delay, and evaluates fast tracking to recover time. Because the change affects the baseline finish date, the PM raises a change request for approval and then updates the baseline and schedule once approved.

PMP Example Question

During execution, the team reports multiple delays on critical activities. What is the most appropriate next step in Control Schedule?

  1. Rebaseline the schedule immediately to reflect the new dates.
  2. Analyze impacts, update actuals, forecast outcomes, and submit a change request for any baseline changes.
  3. Ask the sponsor to extend the project deadline informally.
  4. Add more resources to all late activities without reviewing the critical path.

Correct Answer: B — Analyze, update, forecast, and manage changes through the change control process

Explanation: Control Schedule requires measuring performance, updating the schedule, forecasting, and processing any needed baseline changes via integrated change control, not rebaselining or making unilateral changes.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More