Control Schedule

A continuous activity that tracks project progress, updates the schedule to reflect actual performance, and governs approved changes to the schedule baseline.

Key Points

  • Compares actual progress against the schedule baseline to identify variances.
  • Updates the schedule model and forecasts completion dates using current performance data (e.g., SV, SPI).
  • Submits and manages change requests to the schedule baseline through integrated change control.
  • May apply techniques such as critical path analysis, what-if analysis, and schedule compression (crashing/fast tracking).

Example

Midway through a software project, several critical-path tasks slip. The project manager records actual start/finish dates, recalculates the critical path, forecasts a two-week delay, and evaluates fast tracking to recover time. Because the change affects the baseline finish date, the PM raises a change request for approval and then updates the baseline and schedule once approved.

PMP Example Question

During execution, the team reports multiple delays on critical activities. What is the most appropriate next step in Control Schedule?

  1. Rebaseline the schedule immediately to reflect the new dates.
  2. Analyze impacts, update actuals, forecast outcomes, and submit a change request for any baseline changes.
  3. Ask the sponsor to extend the project deadline informally.
  4. Add more resources to all late activities without reviewing the critical path.

Correct Answer: B — Analyze, update, forecast, and manage changes through the change control process

Explanation: Control Schedule requires measuring performance, updating the schedule, forecasting, and processing any needed baseline changes via integrated change control, not rebaselining or making unilateral changes.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Run the drill before the incident runs you

Design a 15-minute drill, build a full tabletop and run the room before an incident tests your team. ICS/OT Incident Drills and Tabletop Exercises includes 51 lessons, eight quizzes, four hands-on assignments and the exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course