Estimate at Completion (EAC)

The projected total cost to finish all project work, found by adding the actual cost incurred to date (AC) to the estimated cost needed to complete the remaining work (ETC).

Key Points

  • Estimate at Completion (EAC) forecasts what the project will cost when all work is done.
  • Base formula: EAC = AC + ETC, especially when a fresh, bottom-up ETC is prepared.
  • Common EVM variants include: EAC = AC + (BAC - EV)/CPI, EAC = BAC/CPI, and EAC = AC + (BAC - EV)/(CPI*SPI) depending on assumptions.
  • Related terms: BAC (original total budget), ETC (remaining cost), VAC = BAC - EAC (expected overrun/underrun).

Example

A project has AC = $900,000 at mid-point. The team re-estimates the remaining work (ETC) at $1,300,000. EAC = AC + ETC = $900,000 + $1,300,000 = $2,200,000. If BAC was $2,000,000, then VAC = $2,000,000 - $2,200,000 = -$200,000 (project is forecast to finish $200,000 over budget).

PMP Example Question

A project reports AC = $700k, EV = $600k, BAC = $1.2M, and CPI = 0.75. If you assume the remaining work will continue at the current cost performance, what is the Estimate at Completion?

  1. $1,500,000
  2. $1,600,000
  3. $1,300,000
  4. $500,000

Correct Answer: A — EAC (total forecast cost) using CPI-based formula

Explanation: With performance expected to continue, EAC = AC + (BAC - EV)/CPI = 700,000 + (1,200,000 - 600,000)/0.75 = 700,000 + 800,000 = 1,500,000.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course