Control Schedule

A continuous activity that tracks project progress, updates the schedule to reflect actual performance, and governs approved changes to the schedule baseline.

Key Points

  • Compares actual progress against the schedule baseline to identify variances.
  • Updates the schedule model and forecasts completion dates using current performance data (e.g., SV, SPI).
  • Submits and manages change requests to the schedule baseline through integrated change control.
  • May apply techniques such as critical path analysis, what-if analysis, and schedule compression (crashing/fast tracking).

Example

Midway through a software project, several critical-path tasks slip. The project manager records actual start/finish dates, recalculates the critical path, forecasts a two-week delay, and evaluates fast tracking to recover time. Because the change affects the baseline finish date, the PM raises a change request for approval and then updates the baseline and schedule once approved.

PMP Example Question

During execution, the team reports multiple delays on critical activities. What is the most appropriate next step in Control Schedule?

  1. Rebaseline the schedule immediately to reflect the new dates.
  2. Analyze impacts, update actuals, forecast outcomes, and submit a change request for any baseline changes.
  3. Ask the sponsor to extend the project deadline informally.
  4. Add more resources to all late activities without reviewing the critical path.

Correct Answer: B — Analyze, update, forecast, and manage changes through the change control process

Explanation: Control Schedule requires measuring performance, updating the schedule, forecasting, and processing any needed baseline changes via integrated change control, not rebaselining or making unilateral changes.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course