5.12 Estimate Costs
| 5.12 Estimate Costs | ||
|---|---|---|
| Inputs | Tools & Techniques | Outputs |
Replace this with term.
Purpose & When to Use
- Develop a realistic view of how much the project work will cost so leaders can plan funding, compare options, and set expectations early.
- Used during planning to estimate at activity or work package level, then refined as scope, design, and quotes mature.
- Revisited when scope changes, risks evolve, procurement information arrives, or market rates shift.
- Outputs inform the budget baseline process and provide the basis for future cost control.
Mini Flow (How Itβs Done)
- Collect inputs: scope baseline and WBS, activity list and durations, resource needs and rates, procurement strategy and quotes, risk register, lessons learned, cost policies, taxes, and currency assumptions.
- Select estimating approaches: analogous for quick top-down comparisons, parametric for rate-based calculations, three-point for uncertainty, and bottom-up for detailed rollups.
- Obtain market data and vendor pricing where relevant, and analyze bids when multiple offers exist.
- Include quality-related costs, indirects, fees, and life-cycle considerations if required by the business case.
- Calculate activity or work package costs, document assumptions and methods, and show ranges and confidence levels.
- Apply risk-based contingency using reserve analysis, and identify any management reserve held by sponsors if applicable.
- Aggregate estimates to work packages and control accounts aligned to the WBS, time-phase them to the schedule, and reconcile with funding limits.
- Produce cost estimates and a clear basis of estimate, and update the risk register and documents as needed.
Quality & Acceptance Checklist
- Each WBS item has an estimate that matches its defined scope and resources.
- Chosen estimating methods are appropriate for the data available and are explained clearly.
- Rates, units, and quantities are validated, current, and sourced.
- Assumptions, constraints, and exclusions are documented and traceable.
- Direct, indirect, procurement, logistics, taxes, and cost of quality are considered.
- Currency, inflation, and escalation factors are addressed when relevant.
- Risk-based contingency is calculated and linked to specific risks; no double counting with management reserve.
- Estimates are time-phased and consistent with the schedule.
- Estimate ranges and confidence levels are provided where uncertainty exists.
- Peer review completed and stakeholder acceptance recorded.
Common Mistakes & Exam Traps
- Confusing Estimate Costs (activity-level estimating) with Determine Budget (aggregating and setting the cost baseline).
- Providing single-point numbers without a basis, range, or confidence level.
- Ignoring indirect costs, cost of quality, or life-cycle impacts when required.
- Mixing up contingency (for identified risks) with management reserve (for unforeseen work).
- Double counting reserves or applying contingency at multiple rollup levels.
- Using analogous estimates when detailed data is available for bottom-up or parametric methods.
- Failing to refresh estimates after design changes or new vendor quotes.
- Choosing the lowest bid without analyzing total cost of ownership and risk.
- Overlooking currency conversions, inflation, or timing effects on cash flow.
- Assuming earned value techniques are used during estimating rather than during monitoring and control.
PMP Example Question
The sponsor asks for a quick cost figure early in planning to compare alternatives. Detailed design is not yet available. Which technique is most appropriate?
- Analogous estimating.
- Bottom-up estimating.
- Vendor bid analysis.
- Earned value analysis.
Correct Answer: A β Analogous estimating.
Explanation: Analogous uses historical data for fast, top-down estimates when detail is limited. Bottom-up needs detailed scope, vendor bid analysis applies to procurements, and earned value is for performance tracking, not estimating.
HKSM