To-complete performance index

A forward-looking cost efficiency metric that indicates the performance needed on the remaining work to meet a selected cost target (BAC or EAC). It helps determine achievability and guides corrective actions during cost control.

Key Points

  • Shows the required cost efficiency for the remaining work to hit a chosen cost target.
  • Two variants: TCPI(BAC) = (BAC - EV) / (BAC - AC), and TCPI(EAC) = (BAC - EV) / (EAC - AC).
  • Compare TCPI to current CPI: TCPI > 1.0 means tougher-than-planned efficiency is needed; TCPI < 1.0 means the target is more attainable.
  • Use at project, control account, or work package level to focus interventions where they matter.
  • Drives decisions on cost containment, reforecasting (EAC/ETC), and whether to rebaseline.

Purpose of Analysis

  • Assess if the current cost target is realistic given actual performance to date.
  • Quantify how aggressively the team must perform to recover or maintain cost objectives.
  • Support decisions on corrective actions, funding requests, and stakeholder expectations.

Method Steps

  • Select the cost target: original BAC or a revised EAC if management has set a new goal.
  • Gather up-to-date EV and AC at the desired reporting level and period.
  • Calculate TCPI using the appropriate formula for the chosen target.
  • Compare TCPI to the current CPI and team capability to judge achievability.
  • Identify actions: reduce scope, increase productivity, adjust resources, negotiate rates, or revise the forecast.
  • Recommend a path: keep BAC, adopt a new EAC, or rebaseline; document rationale.
  • Monitor TCPI and CPI trends each cycle and update forecasts and reports.

Inputs Needed

  • BAC (Budget at Completion) for the relevant scope.
  • EV (Earned Value) to date for the same scope and time frame.
  • AC (Actual Cost) to date aligned with EV.
  • EAC (Estimate at Completion) if assessing against a revised target.
  • Current CPI (EV/AC) for context and comparison.
  • Approved changes, risk responses, and rate assumptions that affect remaining work.

Outputs Produced

  • Computed TCPI value against BAC and/or EAC.
  • Assessment of achievability versus current CPI and organizational constraints.
  • Recommended corrective or preventive actions and cost control measures.
  • Updated EAC/ETC and cost forecasts as needed.
  • Inputs to stakeholder reports, variance explanations, and management decisions.

Interpretation Tips

  • If TCPI(BAC) is much higher than CPI, meeting BAC is unlikely without significant changes.
  • If TCPI(EAC) is close to current CPI, the revised EAC is consistent with observed performance.
  • Values near 1.0 imply performance must match plan; higher than 1.1 indicates aggressive recovery is required.
  • If AC is at or above the target (BAC or EAC), the denominator approaches zero or turns negative, signaling the target is no longer attainable.
  • Use the same data cut and scope for EV and AC to avoid distorted ratios.

Example

Given BAC = 1,200,000; EV = 500,000; AC = 600,000.

  • TCPI(BAC) = (1,200,000 - 500,000) / (1,200,000 - 600,000) = 700,000 / 600,000 = 1.17.
  • Current CPI = EV / AC = 500,000 / 600,000 = 0.83.
  • Since 1.17 is far above 0.83, holding BAC is unlikely; consider revising EAC and implementing cost controls.
  • If a new EAC = 1,440,000 is adopted, TCPI(EAC) = (1,200,000 - 500,000) / (1,440,000 - 600,000) = 700,000 / 840,000 = 0.83, which aligns with current performance.

Pitfalls

  • Mixing BAC and EAC in the numerator or denominator and getting the wrong ratio.
  • Using stale EV/AC data or mismatched scope definitions between EV and AC.
  • Interpreting TCPI in isolation without comparing to CPI, resource capacity, and constraints.
  • Assuming TCPI > 1.0 is always achievable without considering schedule pressure and risk exposure.
  • Ignoring that a near-zero or negative denominator indicates the target is already unattainable.

PMP Example Question

A project has BAC = 1,200,000, EV = 600,000, and AC = 750,000. Management wants to meet the original BAC. What is the TCPI to achieve BAC?

  1. 0.80.
  2. 1.33.
  3. 0.75.
  4. 1.20.

Correct Answer: B — 1.33.

Explanation: TCPI(BAC) = (BAC - EV) / (BAC - AC) = (1,200,000 - 600,000) / (1,200,000 - 750,000) = 600,000 / 450,000 = 1.33. Values above 1.0 indicate the team must outperform the original plan on remaining work.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!

Explore the Course


Build complete project plans in minutes with AI

Stop spending hours on documentation. Learn how to use AI to create charters, WBS, schedules, risk registers, and executive reports faster—while staying fully in control. This course gives you ready-to-use prompt templates and practical workflows based on real project work. No guesswork, no fluff—just tools you can apply immediately. Backed by Udemy’s 30-day money-back guarantee, so you can start risk-free.

Learn More