complete performance index

A forecasting measure in earned value management that shows the cost efficiency needed on the remaining work to meet a budget target. It compares remaining work to remaining funds and is often referred to as the to-complete performance index (TCPI).

Key Points

  • Also called the to-complete performance index (TCPI); it focuses on future cost efficiency.
  • Calculated as remaining work divided by remaining funds against a chosen target (BAC or EAC).
  • Use BAC when aiming to meet the original budget; use EAC when a new forecast is the agreed target.
  • Interpretation: greater than 1.0 means tougher to achieve, equal to 1.0 means on-plan, less than 1.0 means favorable.
  • Compare the required efficiency to current CPI to judge feasibility and need for corrective action.
  • Based on the same status date and consistent EV data to avoid misleading results.

Purpose of Analysis

  • Assess how efficiently the team must perform on remaining work to hit a cost target.
  • Support decisions on corrective actions, replanning, or accepting a revised forecast.
  • Communicate whether the current performance trend is sufficient to meet objectives.

Method Steps

  • Confirm the status date and ensure EV data is current and consistent.
  • Gather BAC, EV, AC, and the latest approved EAC if applicable.
  • Choose the target: original budget at completion (BAC) or revised estimate at completion (EAC).
  • Compute: for BAC target, (BAC − EV) ÷ (BAC − AC); for EAC target, (BAC − EV) ÷ (EAC − AC).
  • Compare the result to current CPI and evaluate realism based on team capacity and constraints.
  • Decide actions such as cost controls, scope trade-offs, resource changes, or accepting a new EAC.

Inputs Needed

  • BAC - Budget at Completion.
  • EV - Earned Value as of the status date.
  • AC - Actual Cost as of the status date.
  • EAC - Estimate at Completion, if using a revised target.
  • Status date and any approved changes affecting scope or budget.

Outputs Produced

  • The required cost efficiency index to meet BAC or EAC.
  • Feasibility assessment when compared to current CPI and trends.
  • Recommended corrective or preventive actions.
  • Updated forecasts or management communications, as needed.

Interpretation Tips

  • Greater than 1.0 means the team must perform more efficiently than the average cost performance to date.
  • Less than 1.0 means the target is easier than current performance and has some buffer.
  • If the required index is significantly higher than historical CPI, consider revising scope, resources, or accepting a new EAC.
  • Use BAC when management insists on the original budget; use EAC when a realistic, approved forecast replaces BAC.
  • Do not interpret in isolation; review CPI, SPI, risks, and funding constraints.

Example

  • Given: BAC = 1,000, EV = 400, AC = 500.
  • To meet BAC: TCPI = (BAC − EV) ÷ (BAC − AC) = (1,000 − 400) ÷ (1,000 − 500) = 600 ÷ 500 = 1.20.
  • If EAC = 1,100, to meet EAC: TCPI = (1,000 − 400) ÷ (1,100 − 500) = 600 ÷ 600 = 1.00.
  • Interpretation: Hitting the original BAC needs a 1.20 efficiency going forward, which may be challenging; meeting the approved EAC needs 1.00, which is more realistic.

Pitfalls

  • Using the wrong target baseline (mixing BAC and EAC) for the calculation.
  • Comparing TCPI to CPI from a different status date or with inconsistent EV data.
  • Assuming a high TCPI is achievable without checking capacity, constraints, or risks.
  • Ignoring the need to update EAC when repeated high TCPI values are unrealistic.
  • Focusing only on the index and overlooking schedule or scope drivers of cost.

PMP Example Question

A project has BAC = 900, EV = 360, AC = 450, and an approved EAC of 1,000. What does the complete performance index to meet the approved EAC indicate?

  1. TCPI = 1.20, performance must improve significantly.
  2. TCPI = 0.90, performance can be slightly lower than current.
  3. TCPI = 1.00, performance must match plan going forward.
  4. TCPI = 0.80, substantial buffer exists for remaining work.

Correct Answer: C - TCPI = 1.00, performance must match plan going forward.

Explanation: For EAC target: (BAC − EV) ÷ (EAC − AC) = (900 − 360) ÷ (1,000 − 450) = 540 ÷ 550 ≈ 0.98, effectively 1.00. The team needs on-plan cost efficiency for the remaining work.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More