Commit User Stories

The Scrum Team agrees to deliver the Product Owner-approved user stories in the upcoming Sprint, producing a clear set of committed user stories.

Key Points

  • Happens during Sprint Planning after the Product Owner confirms which user stories are ready and prioritized.
  • The team selects stories based on capacity, velocity, and Definition of Done to create a realistic Sprint scope.
  • Results in a Sprint Backlog containing the committed user stories and initial implementation plan.
  • Commitment is a team agreement to deliver; scope may still be refined as learning occurs during the Sprint.

Example

In Sprint Planning, the Product Owner presents the top backlog items with clear acceptance criteria. The developers discuss capacity, estimate effort, and select five user stories they can complete. They move these items into the Sprint Backlog and record them as the committed user stories for the Sprint.

PMP Example Question

During Sprint Planning, which activity creates a definitive set of user stories the team agrees to deliver in the Sprint?

  1. Define Acceptance Criteria
  2. Commit User Stories
  3. Backlog Refinement
  4. Sprint Review Preparation

Correct Answer: B — Commit User Stories

Explanation: Commit User Stories is when the team agrees to deliver Product Owner-approved stories for the Sprint, forming the Sprint Backlog.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More